Renovating an apartment in Istanbul as a foreigner: what to know first

3 min read · Updated

Short answer

Interior renovation in Istanbul doesn't depend on your nationality. Non-structural interior work usually needs no permit, but the building's management plan sets rules on working hours, lift use and debris, so tell the building manager first. Never remove load-bearing walls or columns; structural and façade changes need an engineer, permits and often the other owners' consent. Plan the work in order (pipes and electrics before tiles and paint) and get one itemised quote by room.

Many foreigners buy older flats in Istanbul precisely because they want to renovate: high ceilings in Cihangir, a Bosphorus view in Arnavutköy, a solid 1970s block in Kadıköy that needs a new kitchen and bathroom. Renovating here is very doable, and your nationality makes no legal difference to interior work. What trips people up are building rules, the order of work, and managing a team in a language they don't speak.

Start with the building, not the flat

Every apartment building has a management plan (yönetim planı) and a building manager (yönetici). Before you start:

  • Tell the building manager what you're planning and when.
  • Ask about working hours. Many buildings restrict noisy work to weekdays and certain hours.
  • Ask about the lift (protection, size limits for materials) and debris (where skips can go, how rubble leaves the building).
  • Tell your neighbours. A short note on the door with dates and a phone number buys a lot of goodwill.

We can handle this conversation in Turkish for you.

What needs a permit, and what doesn't

Usually no permit: new kitchen, bathroom renovation, flooring, paint, non-structural partitions, replacing pipes and wiring inside the flat.

Needs proper approvals: anything touching the structure (load-bearing walls, columns, beams, slabs), the façade (windows that change appearance, balcony enclosures), or shared parts of the building. These typically need an engineer, permits and often the other owners' consent.

Never remove or cut load-bearing walls or columns to open up a space. Beyond the legal problems, in an earthquake zone like Istanbul it's genuinely dangerous. A reputable firm will refuse.

Listed buildings

Some older buildings, especially in Beyoğlu, Fatih and along the Bosphorus, are listed (tescilli). Changes to their exterior and structure need permission from the heritage authorities. Interior work may also be restricted. Find out before you buy, or at least before you plan.

The order of work

Doing things out of order is the most expensive mistake in renovation. The rough sequence:

  1. Strip-out: remove what's being replaced.
  2. Hidden systems: new water and waste pipes, electrics, heating pipes. Pressure-test the plumbing and photograph everything before it's covered.
  3. Walls and floors: plaster, screed, levelling.
  4. Waterproofing in wet areas: shower, bathroom floor, balcony.
  5. Tiling.
  6. Kitchen units, doors, sanitaryware.
  7. Paint and finishing.
  8. Cleaning: after-renovation cleaning is its own job.

If someone wants to tile before the pipes are replaced and tested, stop them.

Getting a quote you can actually use

Ask for one itemised quote, broken down by room, with materials named. That lets you decide what to do now and what can wait, and compare quotes line by line. Our guide to hiring a tradesperson in Istanbul covers what a good quote includes.

Renovating from abroad

Plenty of owners renovate while living elsewhere. What makes it work:

  • One responsible contact for the whole job, not five separate trades.
  • Photo updates at each stage, especially before anything is covered up.
  • Every change agreed in writing, with the price, before it's done.
  • Payments linked to finished stages, never far ahead of the work.
  • Decisions on tiles and finishes made from photos and samples sent to you.

Plan it visually

Our renovation planner lets you try layouts and finishes room by room. It's in Turkish for now but mostly visual. When you're ready, tell us about your flat: send photos of the rooms and a rough wish list, and we'll visit, measure and send an itemised quote in English.

Questions about this

Can foreigners renovate property they own in Turkey?

Yes. The same rules apply as for Turkish owners: the building's management plan and the regulations on structural and façade changes.

Do I need a permit to renovate my flat?

Usually not for non-structural interior work like a new kitchen, bathroom, flooring or paint. Changes to the structure, the façade or shared parts of the building are different and need the proper approvals.

Can I enclose my balcony?

A balcony enclosure changes the façade, so it typically needs the other owners' consent and, depending on the building, other approvals. Check with the building manager before ordering it.

How long does a full flat renovation take?

It depends on the size and scope; a single bathroom is days to a couple of weeks, a full flat considerably longer. A proper quote states the planned duration room by room.